The Thames Barrier; Tidal Surge Defence in the UK

Publication date July 25, 2018
Sector Natural Disasters and Coastal Areas
Region name Overseas(England)

Adaptation activity

In the United Kingdom, an adaptation program was launched in 2012, focusing on priority issues such as flood risk management, water resources, and protecting freshwater ecosystems. In order to protect land below sea level, 18 km of flood defences for the Thames estuary were upgraded to augment the Thames Barrier. The gates are closed to prevent flood damage in response to about 10 tidal/storm surges a year. The Thames Barrier is designed to withstand high water surges up to 2030, even accounting for an annual sea level rise of 8mm.

水門「テムズ・バリア」
Fig. 1 Thames Barrier
(Source: GOV.UK, The Thames Barrier)
テムズ川に設置されたテムズバリア
Fig. 2 Thames River and Thames Barrier
(Source: GOV.UK, The Thames Barrier)
Sources and Related Information
Environment Agency, The Thames Barrier project pack 2010
https://web.archive.org/web/20110812172600/http://www.environment-agency.gov.uk/static/documents/Leisure/Thames_Barrier_2010_project_pack.pdf
GOV.UK, The Thames Barrier
https://www.gov.uk/guidance/the-thames-barrier
Ministry of the Environment "STOP THE warming 2017"
https://www.env.go.jp/earth/ondanka/knowledge/Stop2017.pdf